
The default answer for bulk industrial water storage in Kenya is "carbon steel because it is cheapest." The default answer is wrong above roughly 200 cubic metres of capacity, and we publish the math because nobody else does.
Untreated carbon steel in Kenyan humidity reaches end of life in eight to twelve years. Coatings (paint or epoxy) buy you three to five years per coat, so a coated carbon-steel tank needs recoating two to three times per decade.
Each recoat means draining the tank, isolating the supply line, surface-prepping the interior, applying the coating system, and curing. That is one to two weeks of plant downtime plus the recoat cost. Over a thirty-year horizon, that adds up to six to ten recoat cycles, or roughly twelve to twenty weeks of accumulated downtime.
Zinc-aluminium steel (55 percent aluminium, 43.5 percent zinc) forms a self-healing barrier coating. At any cut or scratch, the zinc sacrificially protects the steel underneath. Service life in unsheltered Kenyan conditions runs to thirty years and beyond, with no recoating required during the design life.
At our typical tank sizes above 200 cubic metres, the initial cost premium over carbon steel is in the range of fifteen to twenty-five percent. At twenty years and again at thirty years, the math swings hard in favour of zinc-alum:
Carbon steel still wins under one hundred cubic metres of capacity, where the zinc-alum modular-panel economics do not land yet. We quote both options openly when a tank sits on the boundary; the right answer depends on your replacement tolerance and your downtime cost.
The longer version of this argument, plus a spec sheet for the zinc-alum range, lives on the zinc-alum tanks page.
Electromagnetic, vortex, ultrasonic, Coriolis, or thermal-mass? The medium, the pipe size, and the accuracy you actually need decide which one belongs on the line.
Read26 May 2026Tanks and silos don't stand alone. The platforms, racks, and supports around them are usually the load-bearing schedule risk. Here is how we approach the rest of the steel.
Read26 May 2026Material grade, surface finish, sanitary fittings, and the questions your fabricator wishes you'd ask first.
ReadTell us what you're building. We'll come back with a specification, capacity, and lead time within 48 working hours.
Start02 / Want to talk firstA working call with our engineering team. Walk through what you need, see how we'd approach it, then decide.
Continue03 / Still scopingA field visit to your plant. We measure, photograph, and leave you with a written brief, no commitment from either side.
Continue